Power Plant
Bangpa-In cogeneration Power Plant Project
Owner(Client) : CH. Karnchang Public Co., Ltd.
Location : Bangpa-In
Project : Bangpa-In cogeneration Power Plant Project
Period: 2012
Scope of Service
: Pressure part from VOGT
: Steam Turbine & Generator from GE
: Steel Structure & Pipe Rack from Know-How Transfer
: Stack & Vessel from VOGT
DCAP Project
Owner : District Cooling System and Power Plant Co., Ltd.
Client : Thai Shinryo Co., Ltd.
Location : Suvarnabhumi
Project : DCAP Project
Period: 20-- and 2012
Scope of Service
: HRSG & Presser part from CMI
: Steam Turbine & Generator form Shin Nippon
: Steel Structure & Pipe Rack from Know-How Transfer
: Stack & Vessel from Know-How Transfer
: Boiler & Pressure part from CMI
Glow SPP3-CFB3-NOX Project
Owner(Client) : Glow Energy Public Co., Ltd.
Location : Rayong
Project : Glow SPP3-CFB3-NOX Project
Period: 2012
Scope of Service : Spare Part for NOx Emission Reduction CFB3
Balance of Plant KK1 Project
Owner(Client) : Marubeni Coporation
Location : Khon Kaen
Project : Balance of Plant KK1 Project
Period: 2007
Scope of Service
: Pressure part form Marubeni Corporation
: steam Turbine & Generator from Siemens
: Steel Structure & Pipe Rack from Know-How Transfer
: Stack & Vessel from Know - How Transfer
: Boiler & Pressure part from China Boiler
PTT CUP II Project
Owner : PTT(Thailand) Co., Ltd.
Client : Thai Shinryo Co., Ltd.
Location : Rayong
Project : PTT CUP II Project
Period: 2007
Scope of Service
: HRSG & Presser part from Nem
: Steam Turbine & Generator form G.E.
: Steel Structure & Pipe Rack from Know-How Transfer
: Stack & Vessel from Know-How Transfer
: Boiler & Pressure part from GTB
Balance of Plat SKIC Project
Owner(Client) : Marubeni Coporation
Location : Rachaburi
Project : Balance of Plat SKIC Project
Period: 2006
Scope of Service
: Pressure part form Marubeni Corporation
: steam Turbine & Generator from Siemens
: Steel Structure & Pipe Rack from Know-How Transfer
: Stack & Vessel from Know - How Transfer
: Boiler & Pressure part from Marubeni
TCP's New Cogeneration Project
Owner : Thai Cane Paper(Public) Co., Ltd.
Client : Marubeni Coporation
Location : Kabinburi
Project : TCP's New Cogeneration Project
Period: 2005 - 2006
Scope of Service
: Fabrication and Erection
: Pressure part form Marubeni Japan
: steam Turbine & Generator from Mitsubishi Japan
: Steel Structure & Pipe Rack from Know-How Transdr
: Stack & Vessel from Know - How Transfer
: Boiler & Pressure part from Foster Wheeler
TPI Project
Owner : TPI Co., Ltd.
Client : Nebaska Co., Ltd.
Location : Rayong
Project : TPI Project / Repair Boiler
Period: 2002
Scope of Service
: Pressure part from Know-How Transfer
: Steam Turbine & Generator from Nebaska
: Steel Structure & Pipe Rack from Know-How Transfer
: Boiler & Pressure part form Nebask
TAKUMA Project
Owner(Client) : TAKUMA Co., Ltd.
Location : Pathumthani
Project : -
Period: 2002
Scope of Service
: Pressure part from Know-How Transfer
: Steam Turbine & Generator from Takuma Japan
: Steel Structure & Pipe Rack from Know-How Transfer
: Stack & Vessel from Know-How Transfer
: Boiler & Pressure part form Takuma Japan
United Palm Oil Project
Owner(Client) : United Palm Oil Industrial Co., Ltd.
Location : Krabi
Project : United Palm Oil Project
Period: 2006
Scope of Service
: Steam Turbine & Generator from Shinko
: Steel Structure & Pipe Rack from Know-How Transfer
: Stack & Vessel from Know - How Transfer
: Boiler & Pressure part from Petra